Monday, November 30, 2020

Hall of Fame Aquatic Complex Thanksgiving Update, November 2020


Training Pool


THANKSGIVING UPDATE from COMMANDER IN CHIEF: LAURA VOET

It was a busy Thanksgiving week at the aquatic center, with each piece falling in line!

🍂🍂 Besides pouring the concrete foundation for the new entry building, Neptune Benson Defender regenerative pool filters were placed inside the filtration room building. Utility site work is progressing, dive well and tower structural elements will continue next week after the holiday.

New Pool filters! Neptune Benson regenerative filters! 
Grandstand and Filtration Room structure.
Seating Capacity - 1,522. New Musco sports lighting.
 
              Inside electrical vault

Old Entrance 
Everyone knows the bottom of the pool is a nice, quiet,
peaceful place; now it’s a great spot for lunch too!


I never realized how much dirt is moved in, 
out and around on a construction job site. It is 
a constant process moving it here and there.



1 comment: